Week 1: Demolition, Plumbing, and Waterproofing
Day one is demolition. The old tile, vanity, toilet, and fixtures come out. For a standard bathroom, demo takes one full day. Tub removal adds a few hours. We protect the floors and walls outside the bathroom with heavy-duty coverings and haul everything out the same day when possible.
Days two and three cover plumbing rough-in. If the layout stays the same, this takes one day. Relocating drains or adding new supply lines on a concrete slab takes two to three days because of the saw-cutting and concrete repair involved. Days three through five are waterproofing. We apply liquid membrane to the shower pan, walls, and any wet areas. Each coat needs drying time. In Miami humidity, we allow a full 24 hours between coats and another 24 hours before tiling. Rushing waterproofing in our climate is the number one cause of shower failures. We never skip this step.
Week 2: Tile Installation
Tile installation is the most time-consuming phase and the one that determines how the finished bathroom looks. Shower walls go first, starting from the bottom and working up. Each row needs time to set before adding weight above it, so tall showers may take two days just for the walls. Shower floor mosaics are installed next, carefully following the slope to the drain.
The main bathroom floor tiles go in after the shower is complete. If you are using the same tile in the shower and on the floor, we run the floor tile up to the shower curb for a seamless transition. Feature walls, niches, and accent tile happen during this phase too. A simple tile job with 12x24 porcelain in a straight pattern takes two to three days. Complex patterns with multiple tile types, small mosaics, or large-format pieces that need precise cuts take four to five days. Grouting happens at the end of the tile phase and needs 24 hours to cure before getting wet.
Week 3-4: Fixtures, Glass, and Final Details
Once grout has cured, fixture installation begins. The toilet goes in first because it connects directly to the drain in the slab. The vanity comes next, followed by the faucet, mirror, and lighting. Each piece gets leveled, secured, and connected to plumbing and electrical. This typically takes one to two days.
Glass shower enclosures are measured after tile is complete and usually take 3 to 7 business days to fabricate. This is the most common source of timeline extension. We measure for glass as early in the tile phase as possible to minimize the wait. While waiting for glass, we handle paint touch-ups, caulking, hardware installation, and final electrical work. Once glass arrives and gets installed, we do a final cleaning, check every fixture, test all plumbing, and do a walk-through with you. The bathroom is ready to use the same day the glass goes in. Call (786) 363-7039 to discuss your remodel timeline.
Common Causes of Delays
The most common delay is custom glass fabrication. Standard glass panels can be ready in 3 to 5 days, but custom shapes, notched panels, or specialty glass (frosted, tinted, or textured) take 7 to 10 business days. We order glass as soon as measurements are possible to keep the schedule tight.
Hidden water damage is another delay. When we open walls behind old tubs and showers, we sometimes find rotted framing or mold behind the tiles. This has to be remediated before new waterproofing goes on. In Miami homes built before 1990, this is fairly common. Fixing water damage adds one to three days depending on the extent. Material delays happen occasionally too. If a specific tile is backordered or a vanity ships damaged, we need time to get replacements. We always confirm material availability before starting a project to avoid this. Permit inspections in Miami-Dade can add waiting time if an inspector is not available on our preferred day, though we schedule inspections as early as possible.