A Typical Five to Eight Day Sequence
Day one is usually protection, demolition, tub removal, and inspection of the framing and floor. Next comes plumbing adjustment and preparation of the shower base. Waterproofing needs time to install and cure before tile begins. Wall tile, floor tile, grout, fixtures, and glass follow in that order. The exact sequence can overlap when measurements are taken early and materials are ready.
This schedule assumes a standard tub alcove, normal access, selected materials, and no hidden damage. It also assumes the new shower can use the existing footprint. A custom tile pattern, bench, low entry, or drain move adds work that should be shown in the written schedule.
What Can Add Days?
The most common changes are hidden moisture damage, a drain that must move through the slab, delayed tile or fixture deliveries, and custom glass fabrication. Glass is measured after the tile is installed, so the enclosure may arrive several business days later. A team can reduce that wait by confirming the glass plan early and ordering the hardware ahead of time.
A realistic schedule includes cure periods, not only the hours when someone is physically working in the bathroom. Ask which days the shower will be out of service and when the new shower can first be used.
How to Prepare Before Day One
Choose tile, fixtures, glass style, niche locations, and safety features before demolition. Clear the path from the entry door to the bathroom and remove medicine, towels, and fragile items. Decide which other bathroom the household will use while the shower is out of service. If you live in a condo or an HOA community, confirm delivery hours, elevator rules, parking, and debris procedures before materials arrive.
Ask for a written start date, expected out-of-service period, daily cleanup expectations, and the contact person for changes. Good preparation helps the crew keep the work moving.